Work began in March to build an additional 72 car parks at Paremata park and ride.

Work was due to be complete by the end of June, but is now expected to be complete by the end of November.

This delay is due to an unexpected sub-soil drainage issue on site, which required work to stop while the area was redesigned.

Unfortunately this means we have to continue to reduce parking until the works are complete. If you’re having trouble finding a car park, alternative parking can be found at Mana or Porirua stations.

We apologise for any inconvenience caused by the delay during these works and are doing all we can to have the work completed as quickly as possible.

For more information on the Paremata Park and Ride project please visit the Paremata Station page or call our Metlink team on 0800 801 700.