Petone Station: Major Subway Works
Description
Petone Station subway closed from 18 September until June 2024 for seismic strengthening, drainage works, new lighting and cosmetic upgrades.
Customer Impact
Customers will need to use the overbridge at the northern end of the station to cross between the two platforms. Accessible pedestrian entrances from the carpark and Hutt Road footpaths remain open during the project.
Project Timeline
Sep 01 2023
- Jun 30 2024
Sep 2023
Oct 2023
Nov 2023
Dec 2023
Jan 2024
Feb 2024
Mar 2024
Apr 2024
May 2024
Jun 2024
Phase 1: Site Setup
Sep 1 - Sep 18
Phase 2: Replace floor, improve drainage, improve ramp gradient
Sep 18 - Feb 29
Phase 3: Strengthen walls & tunnel
Mar 1 - May 1
Phase 4: Cosmetic upgrades, lighting, pathway installation
May 1 - Jun 30
This project is experiencing significant delays. New expected opening date is June 2024.